HOW MANY BRICK , CEMENT,SAND REQUIRE FOR 150 CUM CC WORK.

How many brick , cement,sand require for 150 cum cc work? Ratio 1:3:6.
Answer:
1+3+6=10,
Dry volume=150x1.54=231, 1.Brick needed=(231x6x300)/10 = 41580 nos, 2.Sand needed=(231x3)/10 =69.30 cum,
3.Cement needed=(231x1)/(10x0.0347) = 665.71bags