Civil Engineering Estimating
SOME IMPORTANT INFORMATION ABOUT ESTIMATING.
2.Brick require for 1 square meter one brick flat soling=32nos.
3.Brick require for 1 squre meter one layer herring bone bond =52nos.
4.Cement require for 9.3 squre meter neat cement finishing=1/2bag or 25kg
5.A head mason can work 25-30 cum brick work in a day.
HOW MUCH CONSTRUCTION MATERIAL REQUIRE FOR 10 CUM BRICK WORK.
How much construction material require for 10 cum brick work?Ratio 1:6
Answer:
Dry morter=10x35%=3.5cum, 1+6=7, Brick needed=10/(0.254x0.127x0.076)=4079 nos, Cement needed=3.5(1/7)=0.50cum=0.50(1440/50)=14.4bags. Sand needed=(3.5x6)/7=3.00cum
HOW MUCH CONSTRUCTION MATERIALS REQUIRE FOR 12 MM THICK OF 100 SQM CEMENT PLASTERING WORK.
How much construction materials require for 12 mm thick of 100 sqm cement plastering work?Ratio 1:6
Answer:
Dry volume={(100x12x1.5)/1000}=1.8,
Cement needed={(1.8x1x30)/7}=7.71,Nos
Sand needed={(1.8×6)/7}=1.54 cum
A SOAK WELL 25 CM THICK WHOSE INNER DIA IS 150CM AND DEPTH IS 600 CM.HOW MUCH CUM BRICK WORK REQUIRE FOR THIS SOAK WELL CONSTRUCTION.
A soak well 25 cm thick whose inner dia is 150cm and depth is 600 cm.How much cum brick work require for this soak well construction?
Answer:
inner length=[{3.14(inner dia+outer dia)}/2] =[{3.14x(150+200)}/2]=549.5cm=5.495m
brick work needed=5.495x0.25×6=8.24cum.
25CM THICK 1.5M INNER DIA AND 6M DEPTH OF A SOAK WELL.HOW MUCH CONSTRUCTION MATERIALS REQUIRE.
25cm thick 1.5m inner dia and 6m depth of a soak well.How much construction materials require?Ratio 1:6
Answer:
Brick work needed=1[3.14x{(1.5+2)/2}]x0.25x6=8.24 cum,
1+6=7,
Dry morter=8.24x35%=2.884cum, Brick needed=8.24/(0.254x0.127x0.076)=3361 nos, sand needed=2.884(6/7)=2.47cum,
Cement needed=(2.8841)/(7x0.0347)=11.87bags.
HOW MANY ROD REQUIRE FOR 1000 SFT AND 5″ THICK SLAB CASTING.
How many Rod require for 1000 sft and 5″ thick Slab Casting?
Answer:
Total Concrete’s 1% or 1.5% or 2% of Rod should consider in slab casting.
We may consider here 1.5%
Formula is
{(Area x Thickness) } X {(1.5%) X Unit weight of Rod}
So,
[{(1000) X (5/12)}] X {(1.5/100) X 222}
[ note:Unit weight of Rod is 222kg/cft]
=(416.66) X (3.33)
=1387.48kg
DEFINITION OF A CANTILEVER BEAM.
FORMULA FOR LAPPING.
- Formula for lapping in reinforcement at tensile zone is 48d+600 mm (where d as dia).
- Formula for lapping in reinforcement at compression zone is 40d.
Where d is the diameter of Rod.
If we consider 12mm dia rod at column section for lapping,
Then the lapping length at column section should be = 40X12 = 480mm = 0.48m = 19 inch.
ANGLE’S UNIT WEIGHT AS PER METER.
(25mmx25mmx3mm=1.1kg) (25mmx25mmx4mm=1.4kg)
(25mmx25mmx5mm=1.8kg) (30mmx30mmx3mm=1.4kg)
(30mmx30mmx4mm=1.8kg) (30mmx30mmx5mm=2.2kg)
(35mmx35mmx3mm=1.6kg) (35mmx35mmx4mm=2.1kg)
(35mmx35mmx5mm=2.6kg) (35mmx35mmx6mm=3kg)
(40mmx40mmx3mm=1.8kg) (40mmx40mmx4mm=2.4kg)
(40mmx40mmx5mm=3kg) (40mmx40mmx6mm=3.5kg)
(45mmx45mmx3mm=2.1kg) (45mmx45mmx4mm=2.7kg)
(45mmx45mmx5mm=3.4kg) (45mmx45mmx6mm=4kg)
(50mmx50mmx3mm=2.3kg) (50mmx50mmx4mm=3kg)
(50mmx50mmx5mm=3.4kg) (50mmx50mmx6mm=4.5kg)
(55mmx55mmx5mm=4.1kg) (55mmx55mmx6mm=4.9kg)
(55mmx55mmx8mm=6.4kg) (55mmx55mmx10mm=7.9kg)
(60mmx60mmx5mm=4.5kg) (60mmx60mmx6mm=5.4kg)
(60mmx60mmx8mm=7.0kg) (60mmx60mmx10mm=8.6kg)
(65mmx65mmx5mm=4.9kg) (65mmx65mmx6mm=5.8kg)
(65mmx65mmx8mm=7.7kg) (65mmx65mmx10mm=9.4kg)
(70mmx70mmx5mm=5.3kg) (70mmx70mmx6mm=6.3kg)
(70mmx70mmx8mm=8.3kg) (70mmx70mmx10mm=10.2kg)
(75mmx75mmx5mm=5.7kg) (75mmx75mmx6mm=6.8kg)
(75mmx75mmx8mm=8.9kg) (75mmx75mmx10mm=11kg).